Purpose
Explain how an Asset’s Tasks are combined or grouped on different Work Orders in the required scheduling period.
The scheduling period starts on the Starting From date specified on the Generate Proposed Work Orders - Combination Options tab, and is broken up into Grouping Intervals that are a specified number of days.
If the Last Scheduled Date for all Tasks is on or after the Starting From date then the scheduling period and the first grouping interval starts on the Starting From date.
If the Last Scheduled Date for a Task is before the Starting From date then the applicable grouping interval starts on the Starting From date.
The start date of the current grouping interval is relative to the date on which the PWOs are generated (today’s date), and the scheduling period end date is calculated as the start date of the current grouping interval plus the number of days specified for Days to Schedule (in advance).
For example, if today’s date is “2011-01-24”, the Starting From date is “2011-01-01”, Days to Schedule is “30” days and the Grouping Interval is “5” days then the scheduling period starts on “2011-01-01”, the current grouping interval starts on “2011-01-21”, and the scheduling period ends on “2011-02-20”, and comprises of eleven grouping intervals of 5 days each with start dates 01 Jan, 06 Jan, 11 Jan, 16 Jan, 21 Jan, 26 Jan, 31 Jan, 05 Feb, 10 Feb, 15 Feb, and 20 Feb.
If today’s date is “2011-01-01” and the Starting From date is “2011-01-01” then the scheduling period starts on “2011-01-01” and ends on “2011-01-31”, and comprises of eight grouping intervals of 5 days each with start dates 01 Jan, 06 Jan, 11 Jan, 16 Jan, 21 Jan, 26 Jan and 31 Jan.
However, if a Task’s Last Scheduled Date is before the scheduling period’s Starting From date then the Task is scheduled in the applicable grouping intervals before the Starting From date.
In order to optimise the number of Proposed Work Orders that are generated, all Tasks that are scheduled to be executed within a Grouping Interval are combined on one Work Order (if possible) based on their Estimated Next Due Dates and the first date of the Grouping Interval during which the Task is scheduled to be executed, and the same values for the standard filter, split and combination options.
Please note!
Asset “AA” has a Component “C1” to which two Tasks are added.
Proposed Work Orders are generated on “2011-01-24” with the following settings.
The Grouping Interval start date is “2011-01-01” but today’s date is 2011/01/24 (which fall into in the grouping interval that starts on 21 Jan) therefore the scheduling period ends on “2011/02/20”
(i.e. 2011/01/21 + 30 Days to Schedule (in advance), and the dates on which grouping intervals start are:
1 Jan, 6 Jan, 11 Jan, 16 Jan, 21 Jan, 26 Jan, 31 Jan, 05 Feb, 10 Feb, 15 Feb, 20 Feb
The Last Scheduled Date for daily Task “D” is set to “2011-01-01” so the daily Task is due to be executed every day from “2011-01-02” to “2011-01-26” and a PWO is generated every day.
The weekly Task’s Last Scheduled Date is set to “2011-01-01” so the weekly Task is due to be executed on the following Estimated Next Due Dates.
8 Jan, 15 Jan, 22 Jan, 29 Jan
As a result, the weekly Task “W” is grouped with the first daily Task “D” in a grouping interval and a combined PWO will be generated on the following dates:
Task W’s Estimated Next Due Date |
Grouping interval - start date |
Task W scheduled for |
Result |
|
|
1 |
01 Jan |
- |
PWO for Task D generated |
08 Jan |
2 |
06 Jan |
06 Jan |
Combined PWO for Task D + Task W generated |
15 Jan |
3 |
11 Jan |
11 Jan |
Combined PWO for Task D + Task W generated |
|
4 |
16 Jan |
- |
PWO for Task D generated |
22 Jan |
5 |
21 Jan |
21 Jan |
Combined PWO for Task D + Task W generated |
29 Jan |
6 |
26 Jan |
26 Jan |
Combined PWO for Task D + Task W generated |
|
7 |
31 Jan |
- |
PWO for Task D generated |
05 Feb |
8 |
05 Feb |
05 Feb |
Combined PWO for Task D + Task W generated |
12 Feb |
9 |
10 Feb |
10 Feb |
Combined PWO for Task D + Task W generated |
17 Feb |
10 |
15 Feb |
15 Feb |
Combined PWO for Task D + Task W generated |
|
11 |
20 Feb |
16 Feb |
PWO for Task D generated |
The Grouping Interval start date is 2010/12/28 but today’s date is 2011/01/24 (which fall into in the grouping interval that starts on 22 Jan) therefore the scheduling period ends on “2011-02-21”
[i.e. 2010/01/22 + 30 Days to Schedule (in advance)], and the dates on which grouping intervals start are:
28 Dec, 2 Jan, 7 Jan, 12 Jan, 17 Jan, 22 Jan, 27 Jan, 01 Feb, 06 Feb, 11 Feb, 16 Feb
The Last Scheduled Date for daily Task “D” is set to “2011/01/01” so the daily Task is due to be executed every day from “2011/01/02” to “2011/02/20” and a PWO is generated every day.
The weekly Task’s Last Scheduled Date is set to “2011/01/01” so the weekly Task is due to be executed on the following Estimated Next Due Dates:
8 Jan, 15 Jan, 22 Jan, 29 Jan, 05 Feb, 12 Feb, 17 Feb
As a result, the weekly Task “W” is grouped with the daily Task “D” and a combined PWO will be generated on the following dates.
Task W’s Estimated Next Due Date |
Grouping interval - start date |
Task W scheduled for |
Result |
|
|
1 |
28 Dec |
|
PWO for Task D generated |
|
2 |
02 Jan |
|
PWO for Task D generated |
08 Jan |
3 |
07 Jan |
07 Jan |
Combined PWO for Task D + Task W generated |
15 Jan |
4 |
12 Jan |
12 Jan |
Combined PWO for Task D + Task W generated |
|
5 |
17 Jan |
|
PWO for Task D generated |
22 Jan |
6 |
22 Jan |
22 Jan |
Combined PWO for Task D + Task W generated |
29 Jan |
7 |
27 Jan |
27 Jan |
Combined PWO for Task D + Task W generated |
05 Feb |
8 |
01 Feb |
01 Feb |
Combined PWO for Task D + Task W generated |
12 Feb |
9 |
06 Feb |
06 Feb |
Combined PWO for Task D + Task W generated |
|
10 |
11 Feb |
|
PWO for Task D generated |
17 Feb |
11 |
16 Feb |
16 Feb |
Combined PWO for Task D + Task W generated |
Today’s date = “2011/01/24”
Combination option’s Starting From date = “2010/12/28”
Scheduling period ‘s start from date = “2010/01/22”
Calculated as [Combination option’s Starting From date + Grouping Interval], until the Grouping Interval in which the current date occurs.
i.e. 2010/12/28 + 5 days (2 Jan) + 5 days (7 Jan) + 5 days (12 Jan) + 5 days (17 Jan) + 5 days (22 Jan)
Scheduling period ‘s end date = “2011/02/21”
Calculated as [Scheduling period ‘s start date + Days to Schedule (in advance)]
i.e. “2011/01/22” + 30 days = “2011/02/21”
Starting From date of the scheduling period (start date of the current period) = “2010/12/28”
Calculated end date of the scheduling period = “2011/02/20” (Starting From date of the scheduling period + 30 days)
Task W’s Last Scheduled Date is “2010/12/20”
Task D’s Last Scheduled Date is “2010/12/20”
The Grouping Interval start date is 2010/12/28 and today’s date is 2011/01/24 (which fall into in the grouping interval that starts on 22 Jan) therefore the scheduling period ends on 2011/02/21
[i.e. 2011/01/22 + 30 Days to Schedule (in advance)], and the dates on which grouping intervals start are:
28 Dec, 2 Jan, 7 Jan, 12 Jan, 17 Jan, 22 Jan, 27 Jan, 1 Feb, 6 Feb, 11 Feb, 16 Feb
The Last Scheduled Date for daily Task “D” is “2010/12/20” so the daily Task should be executed every day from “2010/12/21” to “2011/02/20”.
The Last Scheduled Date for weekly Task “W” is “2010/12/20” so the weekly Task should be executed on the following Estimated Next Due Dates:
27 Dec, 3 Jan, 10 Jan, 17 Jan, 24 Jan, 31 Jan, 07 Feb, 14 Feb
As a result, the weekly Task “W” is grouped with the daily Task “D” and a combined PWO will be generated on the following dates.
Task W’s Estimated Next Due Date |
Grouping interval - start date |
Task W scheduled for |
Result |
|
27 Dec |
- |
|
- |
Outside the scheduling period |
03 Jan |
1 |
28 Dec |
28 Dec |
Combined PWO for Task D + Task W generated |
|
2 |
02 Jan |
- |
PWO for Task D generated |
10 Jan |
3 |
07 Jan |
07 Jan |
Combined PWO for Task D + Task W generated |
|
4 |
12 Jan |
- |
PWO for Task D generated |
17 Jan |
5 |
17 Jan |
17 Jan |
Combined PWO for Task D + Task W generated |
24 Jan |
6 |
22 Jan |
22 Jan |
Combined PWO for Task D + Task W generated |
31 Jan |
7 |
27 Jan |
27 Jan |
Combined PWO for Task D + Task W generated |
|
8 |
01 Feb |
- |
PWO for Task D generated |
07 Feb |
9 |
06 Feb |
06 Feb |
Combined PWO for Task D + Task W generated |
14 Feb |
10 |
11 Feb |
11 Feb |
Combined PWO for Task D + Task W generated |
|
|
16 Feb |
- |
PWO for Task D generated |
Please note!
The examples can become much more involved, especially when Usage based Tasks are involved, but the fundamentals of combining Tasks on a proposed Work Order as explained above remain as is.